Aikin layi mai tsayi 2020.1
Sabuwar-gina guda-circuit line aikin a Wangda ~ Bitu 110kV, Zuogong birnin, Tibet, shugaba JL/G1A-185/35-26/7 kasa line GJ-70, da jimlar tsawon layin ne 126KM.Total yawa kwana karfe karfe hasumiya shine saiti 311, jimlar nauyi shine ton 3150.Ya ɗauki kwanaki 90 bayan sanya hannu kan odar a watan Oktoba na 2019 don kammala isar da hasumiya a cikin Janairu 2020, kuma an fara aiki da layin gabaɗaya a watan Agusta 2020.